Paragraph 3 Time limit and notificationsI1

England and Wales

(1)

The authorised development must begin no later than the expiration of five years beginning on the start date.

(2)

The undertaker must notify the host authorities—

(a)

within 7 days after the date on which the authorised development begins;

(b)

at least 42 days prior to the anticipated date of commencement of the authorised development, provided that commencement may still lawfully occur if notice is not served in accordance with this sub-paragraph;

(c)

within 7 days after the actual date of commencement of the authorised development;

(d)

at least 42 days prior to the anticipated date of commencement of dual runway operations; and

(e)

within 7 days after the actual commencement of dual runway operations.

Annotations

Commencement

I1

Sch. 2 para. 3 in force at 12.10.2025, see art. 1