Paragraph 32 Western noise mitigation bundI1
England and Wales
(1)
The commencement of dual runway operations must not take place until Work No. 18(b) (replacement noise bund and wall) has been completed.
(2)
Once completed, Work No. 18(b) must not be removed unless otherwise agreed in writing by CBC.
(3)
During the carrying out of Work No. 18(a) (removal of existing western noise bund) and the construction of Work No. 18(b) (replacement noise bund and wall), no ground engine testing may take place on Work No. 4(i) (Taxiway Juliet West Spur) unless otherwise agreed in writing by CBC.
Annotations
Commencement
- I1
Sch. 2 para. 32 in force at 12.10.2025, see art. 1