Paragraph 38 Speed limit monitoringI1
England and Wales
No part of Work Nos. 35, 36 or 37 (surface access works) is to commence until a speed limit monitoring plan for those works has been submitted to and approved in writing by West Sussex County Council (in consultation with Surrey County Council and National Highways).
The speed limit monitoring plan must include—
as a minimum, one survey to be carried out before commencement of the first of Work Nos. 35, 36 or 37 (surface access works) and two surveys to be carried out after completion of the last of those works to assess the changes in traffic speed on the local and strategic highway networks;
the locations to be monitored and the methodology to be used to collect the required data;
the periods over which traffic is to be monitored (each such period to be no longer in duration than 14 days);
the submission of survey data and interpretative reports to West Sussex County Council; and
a description of the manner in which the undertaker would propose to address excessive speeding identified through the monitoring.
The authorised development must be carried out in accordance with the speed limit monitoring plan approved pursuant to sub-paragraph (1) unless otherwise agreed in writing with West Sussex County Council (in consultation with Surrey County Council and National Highways).
Annotations
Commencement
- I1
Sch. 2 para. 38 in force at 12.10.2025, see art. 1