Paragraph 9 Contaminated land and groundwaterI1
England and Wales
In respect of any part of the authorised development where historical data cannot establish that the risk of contaminated land is low, the undertaker must conduct ground investigations prior to that part of the authorised development being commenced. The scope of these investigations must be agreed with the relevant planning authority (in consultation with the Environment Agency on matters related to its functions).
In the event that land affected by contamination, including groundwater, is found at any time when constructing the authorised development which was not previously identified in the environmental statement, it must be reported as soon as reasonably practicable to the relevant planning authority and the Environment Agency, and the undertaker must complete a risk assessment of the contamination in consultation with the relevant planning authority and the Environment Agency.
Where the undertaker’s risk assessment determines that remediation of contamination identified in, on, or under land from detailed site investigations, or as an unexpected discovery, is necessary, a remediation strategy comprising a written scheme and programme for the remedial measures to be taken to render the land fit for its intended purpose must be submitted to and approved in writing by the relevant planning authority (in consultation with the Environment Agency on matters related to its functions).
Any required and agreed remediation must be carried out in accordance with the remediation strategy approved under sub-paragraph (3).
The remediation strategy submitted for approval pursuant to sub-paragraph (3) is to include a verification plan providing details of the data that will be collected in order to demonstrate that the works set out in the remediation strategy are complete and identifying any requirements for longer-term monitoring of pollutant linkages, maintenance and arrangements for contingency action.
Prior to the relevant part of the authorised development being occupied or used (as relevant) a verification report demonstrating the completion of works set out in the approved remediation strategy and the effectiveness of the remediation will be submitted to, and approved in writing by, the relevant planning authority. The report will include results of sampling and monitoring carried out in accordance with the approved verification plan to demonstrate that the site remediation criteria have been met.