OpenLegislation

Paragraph 104 Co-operationI1

England and Wales

(1)

Where in consequence of the proposed construction of any of the authorised development, the undertaker requires the removal of apparatus under this Part of this Schedule or Esso makes requirements for the protection or alteration of apparatus under this Part of this Schedule, the undertaker must use reasonable endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised development and taking into account the need to ensure the safe and efficient operation of Esso’s undertaking and Esso must use its reasonable endeavours to co-operate with the undertaker for that purpose.

(2)

The undertaker and Esso must act reasonably in respect of any given term of this Part of this Schedule and, in particular, (without prejudice to generality) where any consent or expression of satisfaction is required by this Part of this Schedule it must not be unreasonably withheld or delayed.

Annotations

Commencement

I1

Sch. 9 para. 104 in force at 12.10.2025, see art. 1