Article 60A Installations: failure to submit information under article 27AF1
(1)
The operator of an installation is liable to a civil penalty where the operator fails to comply (or to comply on time) with the requirements of article 27A.
(2)
The civil penalty is—
(a)
£5,000; and
(b)
a daily penalty at a daily rate of £500 for each day that the operator fails to comply with the requirements of article 27A, beginning with the day on which the initial notice is given, up to a maximum of £45,000.
Annotations
Textual amendments
- F1
Art. 60A inserted (1.1.2025) by The Greenhouse Gas Emissions Trading Scheme (Amendment) (No. 2) Order 2024 (S.I. 2024/1366), arts. 2(2)(b), 24