OpenLegislation

Paragraph 60 Limitation of scopeF1

The verifier may conclude that the scope of the verification referred to in paragraph 59(3)(b) is too limited in any of the following situations—

(a)

data are missing that prevent a verifier from obtaining the evidence required to reduce the verification risk to the level needed to obtain reasonable assurance;

(b)

the emissions monitoring plan is not issued by the regulator;

(c)

the emissions monitoring plan does not provide sufficient scope or clarity to conclude on the verification;

(d)

the maritime operator has failed to make sufficient information available to enable the verifier to carry out the verification.

Annotations

Textual amendments

F1

Sch. 2A inserted (1.7.2026) by The Greenhouse Gas Emissions Trading Scheme (Amendment) (Extension to Maritime Activities) Order 2026 (S.I. 2026/392), art. 1(1), Sch. 1