Paragraph 19C Capacity increases: grant of applicationF1

(1)

An application to increase an installation’s emissions targets may be granted only if the regulator considers that—

(a)

a capacity increase has been put into operation at the installation;

(b)

the capacity increase is not temporary; and

(c)

the net change in installed capacity at the installation since the reference date (see paragraph 19D) is greater than zero.

(2)

Where the application is granted, the regulator must—

(a)

calculate new emissions targets for each scheme year for which the application is made by increasing the existing emissions target for the scheme year by the increase in the emissions target for the scheme year (see paragraph 19E); and

(b)

vary the installation’s hospital or small emitter permit under paragraph 6 of Schedule 6 by substituting the new emissions targets for the existing targets.

(3)

Except where the installation is a hospital-qualifying installation, if increasing the emissions target for a scheme year would result in an emissions target that exceeds the maximum amount, the emissions target must be increased by such amount as results in an emissions target of the maximum amount.

(4)

Where, after calculating new emissions targets and varying the permit under sub-paragraph (2), the regulator considers that, as a result of incorrect or incomplete evidence in the application, either the application would not have been granted or the installation’s emissions targets would not have been increased to the same extent—

(a)

the regulator may, for the current and future scheme years, determine that the emissions targets should not have been increased or, as the case may be, recalculate the new emissions targets under sub-paragraph (2)(a); and

(b)

if the regulator does either of the things referred to in paragraph (a), the regulator must vary the permit under paragraph 6 of Schedule 6 accordingly.