OpenLegislation

Paragraph 5 F1

United Kingdom

It will be considered technically feasible to install meters in a building not consisting mainly of private dwellings unless—

F2(a)

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(b)

there is more than one entry point for the pipes of the district heat network heating or communal heating into each private dwelling or non-domestic premises in a building or the entry point of the pipes is unknown; or

F3(c)

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Annotations

Textual amendments

F1

Sch. 1 omitted (E.W.S.) (27.1.2026) by virtue of The Heat Networks (Market Framework) (Great Britain) (Amendment) Regulations 2026 (S.I. 2026/7), regs. 2(2)(c), 12(12)

F2

Sch. 1 para. 5(a) omitted (27.11.2020) by virtue of The Heat Network (Metering and Billing) (Amendment) Regulations 2020 (S.I. 2020/1221), regs. 1(2), 14(7)

F3

Sch. 1 para. 5(c) omitted (27.11.2020) by virtue of The Heat Network (Metering and Billing) (Amendment) Regulations 2020 (S.I. 2020/1221), regs. 1(2), 14(7)

Notes on Schedule 1

Textual amendments

F2

Word in Sch. 1 heading substituted (27.11.2020) by The Heat Network (Metering and Billing) (Amendment) Regulations 2020 (S.I. 2020/1221), regs. 1(2), 14(2)

F3

Words in Sch. 1 substituted (27.11.2020) by The Heat Network (Metering and Billing) (Amendment) Regulations 2020 (S.I. 2020/1221), regs. 1(2), 14(3)