OpenLegislation

Section 105CC Timing of conclusion and decisionF1F2

England and Wales

The project authority must—

(a)

reach the reasoned conclusion required by section 105CA(1)(b), and

(b)

decide whether or not to proceed with the relevant construction or improvement,

within a reasonable period of time (having regard to the nature and complexity of the project) beginning on the day on which the authority begins the consideration required by section 105CA(1)(a).

Annotations

Textual amendments

F1

Pt. VA substituted (13.3.1999) by S.I. 1999/369, reg.2

F2

Ss. 105CA-105CD inserted (5.12.2017) by The Environmental Impact Assessment (Miscellaneous Amendments Relating to Harbours, Highways and Transport) Regulations 2017 (S.I. 2017/1070), reg. 1(1), Sch. 2 para. 6 (with Sch. 6 para. 6)

Notes on Part VA

Modifications

C1

Pt. 5A power to amend or repeal conferred (26.12.2023) by Levelling-up and Regeneration Act 2023 (c. 55), ss. 164(3), 255(5), Sch. 14 Pt. 1 (with s. 247)