Paragraph 14 Construction programme for silos and sand shedI1
England, Wales and Scotland
Except for the construction of the foundations of the silos, the sand shed and any hopper, no part of the superstructure of the silos, the sand shed and any hopper must be constructed until after—
(a)
1 March 2013; and
(b)
a bund has been constructed on the north west boundary of the site in accordance with Condition SP13 of the site preparation works permission or, if a development consent order for a new nuclear generating station at Hinkley Point has been implemented by the carrying out of a material operation and contains requirements about bund construction, in accordance with the requirements of that order.
Annotations
Commencement
- I1
Sch. 1 para. 14 in force at 16.8.2012, see art. 1(1)