Part 2 Construction, Maintenance and Use Conditions
England, Wales and Scotland
- 1Geology and land contamination: spoil mound remediation
- 2Working hours
- 3Delivery hours
- 4On-site vehicular movements and maintenance - permitted hours
- 5Landscape and visual: external storage of contractors’ materials
- 6Landscape and visual and air quality: no burning of materials
- 7Noise and vibration: no amplified sound
- 8Directional foghorn
- 9Noise and vibration: noise level
- 10Use noise limit
- 11Noise and vibration: control of noise during construction, maintenance and use
- 12Infill material
- 13Landscape and visual: lighting
- 14Construction programme for silos and sand shed
- 15Alignment of the silos
- 16Height and details of the sand shed and silos
- 17Height of subsidiary works
- 18Storage of oils, fuels, concrete and chemicals
- 19Restriction of aggregate washing
- 20Ecological mitigation and monitoring plan
- 21Habitat management plan
- 22Ecological method statement
- 23Ecology: tree and hedgerow protection
- 24Historic environment: recording of important hedgerows
- 25Historic environment: monitoring of palaeontological remains
- 26Historic: scheduled monument management plan
- 27Drainage: surface water and foul drainage works
- 28Drainage: oil interceptor
- 29Air quality
- 30Residential amenity: information dissemination and complaints handling
- 31Drainage: water & sediment management plan
- 32Engineering details of foreshore access road
- 33Access to foreshore
- 34Flooding: foreshore access
- 35Geology & contaminated land: radiological monitoring
- 36Geology & land: previous contamination unidentified
- 37Groundwater: monitoring
- 38Construction method statement
- 39Construction and environmental management plan
- 40Vegetation clearance
- 41Materials management plan
- 42Site waste management plan
- 43Soil management plan
- 44Limit of closure of coast footpath
- 45Traffic obligations
- 46Bund planting
- 47Maintenance of planting