Paragraph 32 Engineering details of foreshore access roadI1
England, Wales and Scotland
No works to construct the foreshore access road forming part of Work No. 6 must be commenced until engineering construction details for the road including any associated drainage works have been submitted to, and approved in writing by, the local planning authority. The foreshore access road must be constructed and retained in accordance with the approved details. Prior to the removal of the foreshore access road, details of the method and timing of its removal must be submitted to, and approved in writing by, the local planning authority. The foreshore access road must be removed in accordance with the approved details.
Annotations
Commencement
- I1
Sch. 1 para. 32 in force at 16.8.2012, see art. 1(1)