Paragraph 39 Construction and environmental management planI1
England, Wales and Scotland
No construction of the development must commence until a construction and environmental management plan (CEMP) has been submitted to, and approved in writing by, the local planning authority. The CEMP must include details of the following—
site security;
fuel, oil, chemical and concrete storage, bunding, delivery and use;
the method for dealing with both minor and major pollution or other spillages;
the method for dealing with precipitation events exceeding the drainage system capacity;
containment of silt or soil contaminated run off;
disposal of contaminated drainage, including water pumped from excavations;
the means for discharging any silty or discoloured water from excavations over grassland or via a settlement lagoon to remove solids;
methods for protecting watercourses; and
site induction for workforce highlighting pollution prevention and awareness.
The CEMP must be implemented in accordance with the approved details.
Annotations
Commencement
- I1
Sch. 1 para. 39 in force at 16.8.2012, see art. 1(1)