Paragraph 12 Fencing and other means of permanent enclosureI1
England, Wales and Scotland
No stage of the connection works may commence until details of all proposed permanent fences, walls or other means of enclosure of that stage of the connection works have been submitted to and approved by the relevant planning authority.
The details submitted under paragraph (1) must be in accordance with the outline design plan.
Any approved permanent fencing in relation to the connection works in Work No. 7 must be completed before those works are brought into use and must be maintained until the connection works are decommissioned in accordance with the onshore decommissioning plan approved under requirement 25 (onshore decommissioning).