Paragraph 13 Temporary fencing and other temporary means of enclosureI1
England, Wales and Scotland
The details of any temporary fences, walls, or other means of enclosure required for the construction of the connection works must be included in the code of construction practice approved under requirement 18 (which must accord with the outline code of construction practice).
All construction sites must remain securely enclosed at all times during construction of the connection works in accordance with the details approved under sub-paragraph (1) above.
The temporary fencing or other temporary means of enclosure must be removed on completion of that stage of the connection works to the satisfaction of the relevant planning authority.
Annotations
Commencement
- I1
Sch. 1 Pt. 3 para. 13 in force at 3.8.2023, see art. 1
Notes on the whole SI
Textual amendments
- F1
Word in preamble substituted (31.1.2024) by The Hornsea Four Offshore Wind Farm (Correction) Order 2024 (S.I. 2024/117), art. 1(2), Sch.