Paragraph 27 Energy balancing infrastructure safety managementI1
England, Wales and Scotland
(1)
Work No. 7(b) must not commence until an energy balancing infrastructure HazID report (which accords with the outline energy balancing infrastructure HazID report) has been submitted to and approved by the relevant planning authority.
(2)
The energy balancing infrastructure HazID report must be implemented as approved.
Annotations
Commencement
- I1
Sch. 1 Pt. 3 para. 27 in force at 3.8.2023, see art. 1
Notes on the whole SI
Textual amendments
- F1
Word in preamble substituted (31.1.2024) by The Hornsea Four Offshore Wind Farm (Correction) Order 2024 (S.I. 2024/117), art. 1(2), Sch.