Paragraph 28 Stages of authorised developmentI1
England, Wales and Scotland
(1)
The authorised development may not be commenced until a written scheme setting out the stages of construction of the authorised project has been submitted to and approved by the relevant planning authority, in relation to the connection works, or the MMO, in relation to works seaward of MHWS.
(2)
The stages of construction referred to in sub–paragraph (1) must not permit the authorised development to be constructed in more than one overall phase.
(3)
The scheme must be implemented as approved.