Paragraph 23 Stages of constructionI1
England, Wales and Scotland
The licenced activities must not be commenced until a written scheme setting out the stages of construction of the authorised development seaward of MHWS has been submitted to and approved by the MMO in writing.
The stages of construction referred to in sub–paragraph (1) will not permit the authorised development to be constructed in more than one overall phase.
The scheme must be implemented as approved.
The written scheme referred to in sub-paragraph (1) must be submitted to the MMO in writing four months prior to the planned commencement of the licenced activities.