Paragraph 24 Completion of constructionI1

England, Wales and Scotland

(1)

The undertaker must submit a close out report in writing to the MMO and the relevant statutory nature conservation body within three months of the date of completion of construction. The close out report must confirm the date of completion of construction and must include the following details—

(a)

the final number of installed wind turbine generators; and

(b)

the installed wind turbine generator parameters relevant for ornithological collision risk modelling.

(2)

Following completion of construction, no further construction activities can be undertaken under this licence.