Paragraph 23 Piling restrictionI1

England, Wales and Scotland

In the event that driven or part driven pile foundations are to be used to install Work No. 3, no impact piling may be undertaken between 21 August and 23 October each year within the area of Work No. 3 as shown on the offshore works plans unless otherwise agreed in writing by the MMO after consultation with the relevant statutory nature conservation body.

Annotations

Commencement

I1

Sch. 12 para. 23 in force at 3.8.2023, see art. 1

Notes on the whole SI

Textual amendments

F1

Word in preamble substituted (31.1.2024) by The Hornsea Four Offshore Wind Farm (Correction) Order 2024 (S.I. 2024/117), art. 1(2), Sch.