OpenLegislation

Paragraph 6 Ecological management plan above mean low water levelI1

England, Wales and Scotland

(1)

No part of the authorised development above MLWS is to commence within the area of a local planning authority until a written ecological management plan relating to the land above MLWS based on the draft ecological management plan contained in volume 6 of the Environmental Statement and reflecting the survey results and ecological mitigation measures included in the F1Environmental Statement has been submitted to and approved by the local planning authority in consultation with Natural England, the Environment Agency, and to the extent that the plan relates to the intertidal area, the MMO.

(2)

The ecological management plan must include an implementation timetable and must be carried out as approved.

(3)

The ecological management plan must be submitted for approval at least four months prior to the intended start of construction unless otherwise agreed in writing by the local planning authority in consultation with Natural England.

Annotations

Textual amendments

F1

Words in Sch. 1 Pt. 3 para. 6(1) substituted (1.5.2015) by The Hornsea One Offshore Wind Farm (Correction) Order 2015 (S.I. 2015/1280), art. 1, Sch.

Commencement

I1

Sch. 1 Pt. 3 para. 6 in force at 31.12.2014, see art. 1