The Hornsea One Offshore Wind Farm Order 2014
S.I. 2014/3331 · Made 10 December 2014 · Extends to England, Wales and Scotland
Infrastructure Planning
Made 10th December 2014
Coming into force 31st December 2014
The application was examined by a Panel appointed as an Examining authority by the Secretary of State pursuant to Chapter 4 of the 2008 Act and the Infrastructure Planning (Examination Procedure) Rules 2010f3;
The Examining authority, having considered the application with the documents that accompanied it, and the representations made and not withdrawn, has, in accordance with section 74 of the 2008 Act made a report and recommendation to the Secretary of State;
The Secretary of State, having considered the report and recommendation of the Panel, and decided the application, has determined to make an Order giving effect to the proposals comprised in the application with modifications which in his opinion do not make substantial change to the proposals;
The Secretary of State, in exercise of the powers conferred by sections 114, 115, 120, and 149A of the 2008 Act, makes the following Order:C1
Annotations to the whole text
Modifications
- C1
Order modified (1.4.2016) by The Hornsea One Offshore Wind Farm (Amendment) Order 2016 (S.I. 2016/471), arts. 1, 4, Sch.
Footnotes
- f1
-
S.I. 2009/2264. Amended by S.I. 2010/602, 2012/635, 2012/2732.
- f2
- f3
-
S.I. 2010/103. Amended by SI 2012/635.
Contents
- Part 1: Preliminary
- 1Citation and commencement
- 2Interpretation
- Part 2: Principal powers
- 3Development consent granted by the Order
- 4Maintenance of authorised project
- 5Operation of electricity generating stations
- Part 3: Streets
- 6Street works
- 7Application of the 1991 Act
- 8Temporary stopping up of streets
- 9Access to works
- 10Agreements with street authorities
- 11Highway improvements
- Part 4: Supplemental powers
- 12Discharge of water
- 13Authority to survey and investigate the land
- Part 5: Powers of acquisition etc.
- 14Guarantees in respect of payment of compensation
- 15Compulsory acquisition of land
- 16Compulsory acquisition of rights
- 17Time limit for exercise of authority to acquire land compulsorily
- 18Private rights
- 19Application of the Compulsory Purchase (Vesting Declarations) Act 1981
- 20Acquisition of subsoil or airspace only
- 21Acquisition of part of certain properties
- 22Rights under or over streets
- 23Temporary use of land for carrying out the authorised project
- 24Temporary use of land for maintaining authorised project
- 25Statutory undertakers
- 26Recovery of costs of new connections
- Part 6: Operations
- 27Felling or lopping of trees and the removal of hedgerows
- 28Trees subject to tree preservation orders
- Part 7: Miscellaneous and general
- 29Operational land for purposes of the 1990 Act
- 30Disapplication of legislative provisions
- 31Defence to proceedings in respect of statutory nuisance
- 32Procedure in relation to approvals etc under requirements
- 33Abatement of offshore works abandoned or decayed
- 34Transfer of benefit of Order
- 35Deemed marine licences under the Marine and Coastal Access Act 2009
- 36Disapplication of constraints on works in the Humber
- 37Saving for Trinity House
- 38Crown Rights
- 39Certification of plans etc
- 40Protection of Interests
- 41Arbitration
- Signature
- Schedule 1: Authorised Project
- Part 1: Authorised development
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 2Ancillary works
- Part 3: Requirements
- 1Time limits
- 2Detailed design parameters
- 3Colour and lighting
- 4Foundation methods
- 5Archaeology above mean low water level
- 6Ecological management plan above mean low water level
- 7Code of Construction Practice
- 8Landscaping
- 9Implementation and maintenance of landscaping
- 10Decommissioning
- 11Highway accesses
- 12Contaminated land and groundwater
- 13Surface water drainage
- 14Colour and detailed design approval – electrical transmission station
- 15Prohibited access
- 16Port traffic management plan
- 17Co-operation
- 18Control of noise during operational phase
- 19Employment and skills plan
- 20North Coates airfield
- 21Requirement for written approval
- 22Amendments to approved details
- Schedule 2Streets subject to street works
- Schedule 3Streets to be temporarily stopped up
- Schedule 4Access to works
- Schedule 5Land in which only new rights etc., may be acquired
- Schedule 6: Modification of compensation and compulsory purchase enactments for creation of new rights
- Part 1: Compensation enactments
- 1Paragraph 1
- 2Paragraph 2
- Part 2: Application of the 1965 Act
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- Schedule 7: Land of which temporary possession may be taken
- 1Part 1
- 2Part 2
- Schedule 8: Deemed Marine Licences under the Marine and Coastal Access Act 2009 – Deemed Marine Licence 1
- Part 1: Licensed marine activities
- 1Interpretation
- 2Details of licensed activities
- 3Duration
- Part 2: Licence conditions
- 1Design parameters
- 2Design parameters
- 3Design parameters
- 4Design parameters
- 5Design parameters
- 6Notifications and inspections
- 7Aids to navigation
- 8Provision against danger to navigation
- 9Navigational Practice, Safety and Emergency Response
- 10Colour and lighting
- 11Chemicals, drilling and debris
- 12Force majeure
- 13Pre-construction plans and documentation
- 14Pre-construction plans and documentation
- 15Pre-construction plans and documentation
- 16Reporting of engaged agents, contractors and vessels
- 17Equipment and Operation of Vessels Engaged in Licensed Activities
- 18Pre-construction monitoring and surveys
- 19Construction monitoring
- 20Post construction
- 21Amendments to details
- 22Offshore Decommissioning
- Schedule 9: Deemed Marine Licences under the Marine and Coastal Access Act 2009 – Deemed Marine Licence 2
- Part 1: Licensed marine activities
- 1Interpretation
- 2Details of licensed activities
- 3Duration
- Part 2: Licence conditions
- 1Design parameters
- 2Design parameters
- 3Design parameters
- 4Design parameters
- 5Design parameters
- 6Notifications and inspections
- 7Aids to navigation
- 8Provision against danger to navigation
- 9Navigational Practice, Safety and Emergency Response
- 10Colour and lighting
- 11Chemicals, drilling and debris
- 12Force majeure
- 13Pre-construction plans and documentation
- 14Pre-construction plans and documentation
- 15Pre-construction plans and documentation
- 16Reporting of engaged agents, contractors and vessels
- 17Equipment and Operation of Vessels Engaged in Licensed Activities
- 18Pre-construction monitoring and surveys
- 19Construction monitoring
- 20Post construction
- 21Amendments to details
- 22Offshore Decommissioning
- Schedule 10: Deemed Marine Licences under the Marine and Coastal Access Act 2009 – Deemed Marine Licence 3
- Part 1: Licensed marine activities
- 1Interpretation
- 2Details of licensed activities
- 3Duration
- Part 2: Licence conditions
- 1Design parameters
- 2Design parameters
- 3Design parameters
- 4Design parameters
- 5Design parameters
- 6Notifications and inspections
- 7Aids to navigation
- 8Provision against danger to navigation
- 9Navigational Practice, Safety and Emergency Response
- 10Colour and lighting
- 11Chemicals, drilling and debris
- 12Force majeure
- 13Pre-construction plans and documentation
- 14Pre-construction plans and documentation
- 15Pre-construction plans and documentation
- 16Reporting of engaged agents, contractors and vessels
- 17Equipment and Operation of Vessels Engaged in Licensed Activities
- 18Pre-construction monitoring and surveys
- 19Construction monitoring
- 20Post construction
- 21Amendments to details
- 22Offshore Decommissioning
- Schedule 11: Deemed Marine Licences under the Marine and Coastal Access Act 2009 – Deemed Marine Licence 4
- Part 1: Licensed marine activities
- 1Interpretation
- 2Details of licensed activities
- 3Duration
- Part 2: Licence conditions
- 1Design parameters
- 2Design parameters
- 3Design parameters
- 4Design parameters
- 5Design parameters
- 6Notifications and inspections
- 7Aids to navigation
- 8Provision against danger to navigation
- 9Navigational Practice, Safety and Emergency Response
- 10Colour and lighting
- 11Chemicals, drilling and debris
- 12Force majeure
- 13Pre-construction plans and documentation
- 14Pre-construction plans and documentation
- 15Pre-construction plans and documentation
- 16Reporting of engaged agents, contractors and vessels
- 17Equipment and Operation of Vessels Engaged in Licensed Activities
- 18Pre-construction monitoring and surveys
- 19Construction monitoring
- 20Post construction
- 21Offshore Decommissioning
- 22Restrictions in intertidal area and Humber Estuary Special Area of Conservation
- 23Amendments to details
- Schedule 12: Protective provisions
- Part 1: Protection for Environment Agency and drainage authorities
- 1Paragraph 1
- 2Paragraph 2
- 3Paragraph 3
- 4Paragraph 4
- 5Paragraph 5
- 6Paragraph 6
- 7Paragraph 7
- 8Paragraph 8
- 9Paragraph 9
- 10Paragraph 10
- Part 2: Protection for Network Rail Infrastructure limited
- 11Paragraph 11
- 12Paragraph 12
- 13Paragraph 13
- 14Paragraph 14
- 15Paragraph 15
- 16Paragraph 16
- 17Paragraph 17
- 18Paragraph 18
- 19Paragraph 19
- 20Paragraph 20
- 21Paragraph 21
- 22Paragraph 22
- 23Paragraph 23
- 24Paragraph 24
- 25Paragraph 25
- 26Paragraph 26
- 27Paragraph 27
- 28Paragraph 28
- 29Paragraph 29
- 30Paragraph 30
- Part 3: Protection for operators of electronic communications code networks
- 31Paragraph 31
- 32Paragraph 32
- 33Paragraph 33
- 34Paragraph 34
- Part 4: For the protection of utility undertakers
- 35Paragraph 35
- 36Paragraph 36
- 37Paragraph 37
- 38Paragraph 38
- 39Paragraph 39
- 40Paragraph 40
- 41Paragraph 41
- 42Paragraph 42
- 43Paragraph 43
- Part 5: For the protection of Associated British Ports
- 44Paragraph 44
- 45Paragraph 45
- 46Paragraph 46
- 47Paragraph 47
- 48Paragraph 48
- 49Paragraph 49
- 50Paragraph 50
- 51Paragraph 51
- 52Paragraph 52
- 53Paragraph 53
- 54Paragraph 54
- 55Paragraph 55
- 56Paragraph 56
- Part 6: For the protection of Anglian Water Services limited
- 57Paragraph 57
- 58Paragraph 58
- 59Paragraph 59
- 60Paragraph 60
- 61Paragraph 61
- 62Paragraph 62
- 63Paragraph 63
- 64Paragraph 64
- 65Paragraph 65
- 66Paragraph 66
- 67Paragraph 67
- 68Paragraph 68
- 69Paragraph 69
- 70Paragraph 70
- 71Paragraph 71
- Part 7: For the protection of Centrica plc
- 72Paragraph 72
- 73Paragraph 73
- 74Paragraph 74
- 75Paragraph 75
- 76Paragraph 76
- 77Paragraph 77
- 78Paragraph 78
- 79Paragraph 79
- 80Paragraph 80
- Part 8: For the protection of VPI Immingham LLP
- 81Paragraph 81
- 82Paragraph 82
- 83Paragraph 83
- 84Paragraph 84
- 85Paragraph 85
- Part 9: For the protection of Phillips 66 limited
- 86Paragraph 86
- 87Paragraph 87
- 88Paragraph 88
- 89Paragraph 89
- 90Paragraph 90
- Part 10: For the protection of C.GEN Killingholme limited
- 91Paragraph 91
- 92Paragraph 92
- 93Paragraph 93
- 94Paragraph 94
- 95Paragraph 95
- 96Paragraph 96
- 97Paragraph 97
- 98Paragraph 98
- 99Paragraph 99
- 100Paragraph 100
- 101Paragraph 101
- 102Paragraph 102
- 103Paragraph 103
- 104Paragraph 104
- 105Paragraph 105
- 106Paragraph 106
- 107Paragraph 107
- 108Paragraph 108
- 109Paragraph 109
- Part 11: For the protection of ConocoPhillips (UK) Limited
- 110Paragraph 110
- 111Paragraph 111
- 112Paragraph 112
- 113Paragraph 113
- 114Paragraph 114
- Explanatory note