Paragraph 17 Co-operationI1

England, Wales and Scotland

(1)

Prior to the submission of the pre-construction plans and documentation required to be submitted to the MMO for approval under Condition 13 of each of the deemed marine licences set out in Schedules 8 to 11 the undertaker who is the licence-holder under the relevant licence must provide a copy of the plans and documentation to the other undertakers.

(2)

The other undertakers must provide any comments on the plans and documentation to the licence-holder within 14 days of receipt of the plans and documentation.

(3)

The licence-holder shall participate in liaison meetings with other undertakers as requested from time to time by the MMO in writing in advance, which meetings shall be chaired by the MMO and shall consider such matters as are determined by the MMO relating to the efficient operation of a deemed marine licence where it has an impact on the efficient operation of any other deemed marine licence issued under this Order (including as varied or transferred).

Annotations

Commencement

I1

Sch. 1 Pt. 3 para. 17 in force at 31.12.2014, see art. 1