Paragraph 82 I1
England, Wales and Scotland
No less than 28 days before commencing any part of the authorised development or the operation of the authorised development which is near to and would or may have an effect on the operation and maintenance of the pipeline and access to it, the undertaker must submit to VPI plans and sections of the proposed works and such further particulars as VPI may, within 28 days from the day on which plans and sections are submitted under this paragraph, reasonably require.
Annotations
Commencement
- I1
Sch. 12 para. 82 in force at 31.12.2014, see art. 1