Paragraph 12 Force majeureI1

England, Wales and Scotland

If, due to stress of weather or any other cause, the master of a vessel determines that it is necessary to deposit—

(a)

authorised deposits outside of Wind Farm Area 2 or disposal site reference HU206 (Hornsea Project One Subzone 1); or

(b)

unauthorised deposits within or outside of Wind Farm Area 2 or disposal site reference HU206 (Hornsea Project One Subzone 1),

because the safety of human life and/or of the vessel is threatened, full details of the circumstances of the deposit shall be notified to the MMO within 48 hours.

Annotations

Commencement

I1

Sch. 9 para. 12 in force at 31.12.2014, see art. 1