OpenLegislation

Paragraph 91 I1

England, Wales and Scotland

(1)

The following provisions apply to govern the relationship between the undertaker and C.GEN unless otherwise agreed in writing between the undertaker and C.GEN. For the avoidance of doubt, paragraphs 92, 93(1) and 106(1) of the following provisions shall apply only in respect of such parts of the grid connection land in which C.GEN have a land interest or have powers under any order or statutory instrument to acquire such an interest (whenever granted).

(2)

In this Part of this Schedule—

  • “approving party” means the party from whom an approval should be, has been or should have been obtained under the terms of this Part, and shall be the undertaker in the case of specified work by C.GEN, and C.GEN in the case of specified work by the undertaker;

  • “C.GEN” means C.GEN Killingholme Limited (Company number 06422434), whose principal office is at 130 Shaftesbury Avenue, London W1D 5EU;

  • “C.GEN relevant land” means the area of land shown coloured yellow on the plan;

  • “construction” includes execution, placing, altering, replacing, reconstruction, relaying, maintenance, extensions, enlargement and removal and “construct” and “constructed” are construed accordingly;

  • “crossing zones” means those areas of land shown coloured green on the plan;

  • “dominant land” means the Order land shown numbered 404 on the land plans;

  • “drainage ditch” means the ditch shown by a black line marked ‘Drain’ on the plan;

  • “Hornsea Project Substation Site” means the substation site shown outlined in pink on the plan;

  • “grid connection land” means the C.GEN relevant land, the thermal buffer zone and the crossing zones;

  • “the plan” means the plan entitled the C.GEN Protective Provisions plan and certified as the C.GEN protective provisions plan by the Secretary of State for the purposes of this Part of this Schedule;

  • “plans” includes sections, drawings, specifications, designs, design data, software, soil reports, calculations, descriptions (including descriptions of methods of construction), staging proposals, programmes and details of the extent, timing and duration of any proposed occupation of the relevant land;

  • “promoting party” means the party who is seeking, has sought or should have sought an approval under the terms of this Part of this Schedule and shall be the undertaker in the case of specified work by the undertaker, and C.GEN in the case of specified work by C.GEN;

  • “pylon land” means the area of land shown cross-hatched in black on the plan;

  • “servient land” means any pond, ponds or any watercourse on land under the ownership of C.GEN as at the date of this Order;

  • “specified work” means so much of any work or operation by the undertaker or C.GEN as is in, on, under or over the grid connection land; and

  • “thermal buffer zone” means the area of land shown coloured red on the plan.

Annotations

Commencement

I1

Sch. 12 para. 91 in force at 31.12.2014, see art. 1