Paragraph 13 Surface and foul water drainageI1

England and Wales

(1)

No phase of the connection works shall commence until for that phase written details of the surface and (if any) foul water drainage system (including means of pollution control) have, after consultation with the relevant sewerage and drainage authorities and the Environment Agency, been submitted to and approved by the lead local flood authority.

(2)

The surface and foul water drainage system for each phase must be constructed and maintained in accordance with the approved details.

Annotations

Commencement

I1

Sch. 1 Pt. 3 para. 13 in force at 22.1.2021, see art. 1

Notes on the whole SI

Textual amendments

F1

Preamble: bracket omitted (21.5.2021) by virtue of The Hornsea Three Offshore Wind Farm (Correction) Order 2021 (S.I. 2021/599), art. 1(2), Sch.