OpenLegislation

Article 8 Operation of generating stationsI1

England, Wales and Scotland

(1)

Optimus Wind is authorised to operate the generating station comprised in the Project A works.

(2)

Breesea is authorised to operate the generating station comprised in the Project B works.

(3)

This article does not relieve Optimus Wind or Breesea of any requirement to obtain any permit or licence under any other legislation that may be required to authorise the operation of a generating station.

Annotations

Commencement

I1

Art. 8 in force at 7.9.2016, see art. 1(2)