Paragraph 4 I1
England, Wales and Scotland
Before commencing the construction of the specified works, the relevant undertaker must furnish to A. B. Ports for its approval, which it must not unreasonably withhold, plans of the specified works showing the general mode of construction, depth and method of trenching and possible cable protection; and the specified works—
must not be constructed otherwise than in accordance with the plans approved by A. B. Ports; and
must be executed to the reasonable satisfaction of A. B. Ports.
When submitting plans in respect of the specified works to the Secretary of State pursuant to article 40 (certification of plans, etc.), the relevant undertaker must—
send a copy of those plans to A. B. Ports; and
on receipt of approval of plans or of any conditions or restrictions imposed by the Secretary of State, send a copy to A. B. Ports.
If A. B. Ports fails to express its disapproval of any plans within 56 days after they have been furnished to it under sub-paragraph (1), it is deemed to have approved them.
Annotations
Commencement
- I1
Sch. 12 Pt. 5 para. 4 in force at 7.9.2016, see art. 1(2)