OpenLegislation

Paragraph 5 I1

England, Wales and Scotland

The relevant undertaker must give to A. B. Ports—

(a)

not less than 14 days’ written notice of its intention to commence the construction of the specified works; and

(b)

not more than 14 days after completion of the construction, written notice of such completion.

Annotations

Commencement

I1

Sch. 12 Pt. 5 para. 5 in force at 7.9.2016, see art. 1(2)