Section 34 Extension of period for completion of work or demolitionI1
(1)
The local authority may, at any time, extend the period within which any—
(a)
work required by a work notice, or
(b)
demolition required by a demolition notice,
must be completed by such period as it considers reasonable.
(2)
But such a period may be extended only where the local authority—
(a)
considers that satisfactory progress has been made in carrying out the work or demolition, or
(b)
has received a written undertaking from the owner stating that the work or demolition will be completed by a later date which the authority considers satisfactory.
(3)
The local authority must give notice of any extension in accordance with section 62.
Annotations
Commencement
- I1
S. 34 in force at 1.4.2009 by S.S.I. 2009/122, art. 3