The HyNet Carbon Dioxide Pipeline Order 2024

S.I. 2024/436 · Made 20 March 2024 · Extends to England, Wales and Scotland

Up to date with all changes known to legislation.gov.uk, revised to 16 October 2024.

Infrastructure Planning

Made 20th March 2024

Coming into force 11th April 2024

An application has been made to the Secretary of State under section 37 of the Planning Act 2008f1 (“the 2008 Act”), and in accordance with the Infrastructure Planning (Applications: Prescribed Forms and Procedures) Regulations 2009f2 for an order granting development consent.

The application was examined by a panel of 2 members appointed by the Secretary of State (“the Panel”) pursuant to section 61 and 65 of Part 6 of the 2008 Act and carried out in accordance with Chapter 4 of Part 6 of the 2008 Act and the Infrastructure Planning (Examination Procedure) Rules 2010f3.

The Panel has submitted a report and recommendation to the Secretary of State in accordance with section 74(2) of the 2008 Act.

The Secretary of State has considered the report and recommendation of the Panel, has taken into account the environmental information in accordance with regulation 4 of the Infrastructure Planning (Environmental Impact Assessment) Regulations 2017f4, and has had regard to the documents and matters referred to in section 105(2) of the 2008 Act.

In accordance with section 131(5) of the 2008 Act the Secretary of State is satisfied that where this Order authorises the compulsory acquisition of land forming part of an open space special category land that land is less than 200 square metres in extent and the giving in exchange of other land is unnecessary, whether in the interests of the persons, if any, entitled to rights of common or other rights or in the interests of the public.

The Secretary of State is satisfied that open space within the Order land, when burdened with any new rights authorised for compulsory acquisition under the terms of this Order, will be no less advantageous than it was before such acquisition, to the persons whom it is vested, other persons, if any, entitled to rights of common or other rights, and the public, and that, accordingly, section 132(3) of the 2008 Act applies.

The Secretary of State, having decided the application, has determined to make an Order granting development consent for the development described in the application with modifications which in the opinion of the Secretary of State do not make any substantial changes to the proposals comprised in the application.

The Secretary of State, in exercise of the powers conferred by sections 114, 115, 120, 122, 123, 131 and 132 of the 2008 Act, makes the following Order:

Annotations to the whole text

Footnotes

f1

2008 c. 29. Section 37 was amended by section 128(2) and Schedule 13, Part 1, paragraphs 1 to 5 of the Localism Act 2011 (c. 20).

f2

S.I. 2009/2264.

f3

S.I. 2010/103. This instrument was amended by S.I. 2012/635.

f4

S.I. 2017/572.

Contents

  1. Part 1: Preliminary
  2. 1Citation and commencement
  3. 2Interpretation
  4. Part 2: Principal Powers
  5. 3Development consent etc. granted by the Order
  6. 4Operation and use of the authorised development
  7. 5Power to maintain the authorised development
  8. 6Limits of deviation
  9. 7Benefit of the Order
  10. 8Application and modification of legislative provisions
  11. 9Defence to proceedings in respect of statutory nuisance
  12. Part 3: Streets
  13. 10Street works
  14. 11Power to alter layout, etc. of streets
  15. 12Application of the 1991 Act
  16. 13Temporary restriction of public rights of way
  17. 14Stopping up of public rights of way
  18. 15Temporary restriction of use of streets
  19. 16Access to works
  20. 17Agreements with street authorities
  21. 18Use of private roads
  22. 19Traffic regulation
  23. Part 4: Supplemental powers
  24. 20Discharge of water
  25. 21Maintenance of drainage works
  26. 22Authority to survey and investigate the land
  27. 23Protective work to buildings
  28. Part 5: Powers of Acquisition
  29. 24Compulsory acquisition of land
  30. 25Time limit for exercise of authority to acquire land compulsorily
  31. 26Compulsory acquisition of rights and restrictive covenants
  32. 27Statutory authority to override easements and other rights
  33. 28Compulsory acquisition of land: minerals
  34. 29Private rights
  35. 30Application of the 1981 Act
  36. 31Acquisition of subsoil or airspace only
  37. 32Modification of Part 1 of the 1965 Act
  38. 33Rights under or over streets
  39. 34Temporary use of land for carrying out the authorised development
  40. 35Temporary use of land for maintaining the authorised development
  41. 36Statutory undertakers
  42. 37Recovery of costs of new connections
  43. Part 6: Miscellaneous and general
  44. 38Application of landlord and tenant law
  45. 39Felling or lopping of trees and removal of hedgerows
  46. 40Trees subject to Tree Preservation Orders
  47. 41Crown rights
  48. 42Protective provisions
  49. 43Operational land for the purposes of the 1990 Act
  50. 44Certification of plans, etc.
  51. 45Service of notices
  52. 46No double recovery
  53. 47Arbitration
  54. Signature
  55. Schedule 1
  56. 1Authorised development
  57. 2Ancillary works
  58. Schedule 2: Requirements
  59. Part 1: Requirements
  60. 1Interpretation
  61. 2Time limits
  62. 3Stages of authorised development
  63. 4Paragraph 4
  64. 5Scheme design
  65. 6Construction environmental management plan
  66. 7Construction traffic
  67. 8Highway accesses
  68. 9Surface water drainage
  69. 10Contaminated land and groundwater: Part A - Stanlow
  70. 11Archaeology
  71. 12Landscape and ecological management plan
  72. 13Ecological surveys
  73. 14Biodiversity Net Gain
  74. 15Construction hours
  75. 16Operational noise
  76. 17Provision of ‘as built’ details
  77. 18Restoration of land
  78. 19Operational and maintenance environmental management plan
  79. 20Decommissioning environmental management plan
  80. 21Written approval
  81. 22Amendments to approved details
  82. 23Anticipatory steps towards compliance with any requirement
  83. Part 2: Applications made under requirements
  84. 24Paragraph 24
  85. 25Multiple discharging authorities
  86. 26Further information
  87. 27Fees
  88. 28Appeals
  89. 29Outcome of appeals
  90. 30Interpretation
  91. Schedule 3: Streets subject to street works
  92. 1Streets subject to permanent street works
  93. 2Streets subject to temporary street works
  94. Schedule 4: New means of access
  95. 1New permanent means of access from the public highway
  96. 2New temporary means of access from the public highway
  97. 3New private means of access
  98. Schedule 5Streets to be temporarily closed or restricted
  99. Schedule 6: Public rights of way to be temporarily restricted and stopped up
  100. 1Public rights of way to be temporarily restricted
  101. 2Public rights of way to be stopped up
  102. Schedule 7: Land of which only temporary possession may be taken
  103. 1Land of which only temporary possession may be taken
  104. 2Land of which only temporary possession for access may be taken
  105. Schedule 8Land in which only new rights etc., may be acquired
  106. Schedule 9: Modification of compensation and compulsory purchase enactments for creation of new rights
  107. 1Compensation enactments
  108. 2Compensation enactments
  109. 3Compensation enactments
  110. 4Application of Part 1 of the 1965 Act
  111. 5Application of Part 1 of the 1965 Act
  112. Schedule 10: Protective provisions
  113. Part 1: Protection for electricity, gas, water and sewerage undertakers
  114. 1Paragraph 1
  115. 2Paragraph 2
  116. 3On street apparatus
  117. 4Acquisition of land
  118. 5Removal of apparatus
  119. 6Facilities and rights for alternative apparatus
  120. 7Retained apparatus
  121. 8Expenses and costs
  122. 9Expenses and costs
  123. 10Miscellaneous
  124. Part 2: Protection for operators of electronic communications code networks
  125. 11Paragraph 11
  126. 12Paragraph 12
  127. 13Paragraph 13
  128. 14Paragraph 14
  129. Part 3: For the protection of National Grid Electricity Transmission plc as electricity undertaker
  130. 15Application
  131. 16Interpretation
  132. 17On Street Apparatus
  133. 18Apparatus of statutory undertakers in temporarily restricted streets
  134. 19Protective works to buildings
  135. 20Acquisition of land
  136. 21Removal of apparatus
  137. 22Facilities and rights for alternative apparatus
  138. 23Retained apparatus: protection of electricity undertaker
  139. 24Expenses
  140. 25Indemnity
  141. 26Enactments and agreements
  142. 27Co-operation
  143. 28Access
  144. 29Arbitration
  145. 30Notices
  146. Part 4: For the protection of National Gas Transmission plc as gas undertaker
  147. 31Application
  148. 32Interpretation
  149. 33On Street Apparatus
  150. 34Apparatus of statutory undertakers in temporarily restricted streets
  151. 35Protective works to buildings
  152. 36Acquisition of land
  153. 37Removal of apparatus
  154. 38Facilities and rights for alternative apparatus
  155. 39Retained apparatus: protection of gas undertaker
  156. 40Expenses
  157. 41Indemnity
  158. 42Enactments and agreements
  159. 43Co-operation
  160. 44Access
  161. 45Arbitration
  162. 46Notices
  163. Part 5: For the protection of Cadent Gas Limited
  164. 47Application
  165. 48Interpretation
  166. 49On Street apparatus
  167. 50Apparatus of Cadent in stopped up streets
  168. 51Protective works to buildings
  169. 52Acquisition of land
  170. 53Removal of apparatus
  171. 54Facilities and rights for alternative apparatus
  172. 55Retained apparatus: protection of Cadent
  173. 56Expenses
  174. 57Enactments and agreements
  175. 58Co-operation
  176. 59Access
  177. 60Arbitration
  178. 61Notices
  179. Part 6: For the protection of Network Rail
  180. 62Paragraph 62
  181. 63Paragraph 63
  182. 64Paragraph 64
  183. 65Paragraph 65
  184. 66Paragraph 66
  185. 67Paragraph 67
  186. 68Paragraph 68
  187. 69Paragraph 69
  188. 70Paragraph 70
  189. 71Paragraph 71
  190. 72Paragraph 72
  191. 73Paragraph 73
  192. 74Paragraph 74
  193. 75Paragraph 75
  194. 76Paragraph 76
  195. 77Paragraph 77
  196. 78Paragraph 78
  197. 79Paragraph 79
  198. 80Paragraph 80
  199. 81Paragraph 81
  200. Part 7: For the protection of the Canal and River Trust
  201. 82Interpretation
  202. 83Powers requiring the Canal & River Trust’s consent
  203. 84Fencing
  204. 85Survey of waterway
  205. 86Approval of plans, protective works etc.
  206. 87Design of works
  207. 88Notice of works
  208. 89Construction of specified works
  209. 90Prevention of pollution
  210. 91Access to work – provision of information
  211. 92Alterations to the waterway
  212. 93Maintenance of works
  213. 94Repayment of the Canal & River Trust’s fees, etc.
  214. 95Making good of detriment; compensation and indemnity, etc.
  215. 96Arbitration
  216. 97Capitalised sums
  217. Part 8: For the protection of SP Manweb
  218. 98Application
  219. 99Interpretation
  220. 100On Street Apparatus
  221. 101Acquisition of land
  222. 102Removal of apparatus
  223. 103Facilities and rights for alternative apparatus
  224. 104Retained apparatus: Protection of SP Manweb as Electricity Undertaker
  225. 105Expenses
  226. 106Indemnity
  227. 107Enactments and agreements
  228. 108Co-operation
  229. 109Access
  230. 110Arbitration
  231. 111Notices
  232. Part 9: Protection of CF Fertilisers UK Limited
  233. 112Paragraph 112
  234. 113Paragraph 113
  235. 114Rights of access
  236. 115Expenses
  237. 116Expenses
  238. 117Expenses
  239. Part 10: For the protection of Wales and West Utilities
  240. 118Paragraph 118
  241. 119Paragraph 119
  242. 120Apparatus in streets
  243. 121Apparatus in streets
  244. 122Acquisition of land
  245. 123Removal of apparatus
  246. 124Facilities and rights for alternative apparatus
  247. 125Retained apparatus
  248. 126Expenses and costs
  249. 127Expenses and costs
  250. 128Enactments and agreements
  251. Part 11: Protection for Welsh Water
  252. 129Paragraph 129
  253. 130Paragraph 130
  254. 131On street apparatus
  255. 132Acquisition of land
  256. 133Removal of apparatus
  257. 134Facilities and rights for alternative apparatus
  258. 135Retained apparatus
  259. 136Expenses and costs
  260. 137Expenses and costs
  261. 138Miscellaneous
  262. Part 12: For the protection of United Utilities Water Limited (UU Water)
  263. 139Application
  264. 140Interpretation
  265. 141Apparatus of UU Water stopped up in street
  266. 142Discharge of Water, foul and surface water
  267. 143Protective works to buildings
  268. 144Removal of apparatus
  269. 145Facilities and rights for alternative apparatus
  270. 146Retained apparatus: protection of UU Water
  271. 147Expenses
  272. 148Indemnity
  273. 149Enactments and agreements
  274. 150Co-operation
  275. 151Access
  276. 152Arbitration
  277. 153Notices
  278. Part 13: For the protection of United Kingdom Oil Pipelines Limited
  279. 154Paragraph 154
  280. 155Application
  281. 156Interpretation
  282. 157On Street Apparatus
  283. 158Acquisition or possession of land
  284. 159Removal of apparatus
  285. 160UKOP replacement facilities and rights
  286. 161Retained apparatus
  287. 162Expenses and costs
  288. 163Miscellaneous
  289. 164Co-operation
  290. 165Access
  291. 166Arbitration
  292. 167Notices
  293. 168Deviation of authorised development
  294. Part 14: For the protection of PEEL NRE Limited
  295. 169Paragraph 169
  296. 170Paragraph 170
  297. 171Paragraph 171
  298. 172Paragraph 172
  299. 173Paragraph 173
  300. 174Paragraph 174
  301. 175Paragraph 175
  302. 176Paragraph 176
  303. Part 15: Protection of Encirc Limited
  304. 177Paragraph 177
  305. 178Paragraph 178
  306. 179Rights of access
  307. 180Rights of access
  308. 181Rights of access – Grinsome Road to the Protos Site
  309. 182Rights of access – Grinsome Road to the Protos Site
  310. 183Rights of access – Ash Road (South)
  311. 184Rights of Access – Abnormal Loads
  312. 185Railway
  313. 186Construction Traffic Management Plan
  314. 187Co-operation
  315. 188Co-operation
  316. 189Co-operation
  317. 190Specified work
  318. 191Specified work
  319. 192Expenses
  320. 193General
  321. 194Notices
  322. Part 16: For the protection of Welsh Ministers as Strategic Highway Authority
  323. 195Application
  324. 196Interpretation
  325. 197Approvals
  326. 198Approvals
  327. 199Approvals
  328. 200Approvals
  329. 201Approvals
  330. 202Approvals
  331. 203Approvals
  332. 204Approvals
  333. 205Indemnity
  334. 206Indemnity
  335. 207Traffic management
  336. 208Traffic management
  337. 209Inspections
  338. 210Inspections
  339. 211Inspections
  340. 212Reinstatement
  341. 213Reinstatement
  342. 214Reinstatement
  343. 215Notice of completion of Works
  344. 216Notice of completion of Works
  345. 217Notice of completion of Works
  346. 218Notice of completion of Works
  347. 219Arbitration
  348. 220Notices
  349. 221Maintenance
  350. Part 17: For the protection of National Highways Limited
  351. 222Application etc.,
  352. 223Interpretation
  353. 224General
  354. 225General
  355. 226General
  356. 227Prior approvals and security
  357. 228Construction of the specified works
  358. 229Payments
  359. 230Condition survey and as built details
  360. 231Insurance
  361. 232Indemnity
  362. 233Maintenance of the specified works
  363. 234Land
  364. 235Expert Determination
  365. Part 18: For the protection of local highway authorities
  366. 236Paragraph 236
  367. 237Paragraph 237
  368. 238Highway condition and highway assets surveys
  369. 239HGV route remediation
  370. 240Specified work
  371. 241Specified work
  372. Part 19: For the protection of drainage authorities
  373. 242Paragraph 242
  374. 243Paragraph 243
  375. 244Paragraph 244
  376. 245Paragraph 245
  377. 246Paragraph 246
  378. 247Paragraph 247
  379. 248Paragraph 248
  380. 249Paragraph 249
  381. 250Paragraph 250
  382. Part 20: For the protection of Exolum Pipeline System Ltd
  383. 251Application
  384. 252Interpretation
  385. 253Acquisition of Apparatus
  386. 254Acquisition of Apparatus
  387. 255Acquisition of Apparatus
  388. 256Acquisition of Apparatus
  389. 257Removal of Apparatus and Rights for Alternative Apparatus
  390. 258Removal of Apparatus and Rights for Alternative Apparatus
  391. 259Removal of Apparatus and Rights for Alternative Apparatus
  392. 260Removal of Apparatus and Rights for Alternative Apparatus
  393. 261Removal of Apparatus and Rights for Alternative Apparatus
  394. 262Removal of Apparatus and Rights for Alternative Apparatus
  395. 263Removal of Apparatus and Rights for Alternative Apparatus
  396. 264Removal of Apparatus and Rights for Alternative Apparatus
  397. 265Facilities and Rights for Alternative Apparatus
  398. 266Facilities and Rights for Alternative Apparatus
  399. 267Facilities and Rights for Alternative Apparatus
  400. 268Facilities and Rights for Alternative Apparatus
  401. 269Facilities and Rights for Alternative Apparatus
  402. 270Retained Apparatus and Alternative Apparatus: protection
  403. 271Retained Apparatus and Alternative Apparatus: protection
  404. 272Retained Apparatus and Alternative Apparatus: protection
  405. 273Retained Apparatus and Alternative Apparatus: protection
  406. 274Retained Apparatus and Alternative Apparatus: protection
  407. 275Retained Apparatus and Alternative Apparatus: protection
  408. 276Retained Apparatus and Alternative Apparatus: protection
  409. 277Retained Apparatus and Alternative Apparatus: protection
  410. 278Retained Apparatus and Alternative Apparatus: protection
  411. 279Retained Apparatus and Alternative Apparatus: protection
  412. 280Retained Apparatus and Alternative Apparatus: protection
  413. 281Retained Apparatus and Alternative Apparatus: protection
  414. 282Retained Apparatus and Alternative Apparatus: protection
  415. 283Cathodic protection testing
  416. 284Cathodic protection testing
  417. 285Expenses
  418. 286Expenses
  419. 287Expenses
  420. 288Expenses
  421. 289Damage to property and other losses
  422. 290Damage to property and other losses
  423. 291Damage to property and other losses
  424. 292Damage to property and other losses
  425. 293Damage to property and other losses
  426. 294Insurance
  427. 295Insurance
  428. 296Co-operation and reasonableness
  429. 297Co-operation and reasonableness
  430. 298Co-operation and reasonableness
  431. 299Emergency circumstances
  432. 300Emergency circumstances
  433. 301Emergency circumstances
  434. 302Emergency circumstances
  435. 303Escalation of differences
  436. 304Escalation of differences
  437. 305Escalation of differences
  438. 306Dispute resolution
  439. 307Dispute resolution
  440. 308Dispute resolution
  441. 309Dispute resolution
  442. 310Dispute resolution
  443. 311Dispute resolution
  444. 312Dispute resolution
  445. 313Dispute resolution
  446. 314Dispute resolution
  447. 315Miscellaneous
  448. 316Miscellaneous
  449. Part 21: For the protection of the Environment Agency
  450. 317Paragraph 317
  451. 318Paragraph 318
  452. Schedule 11: Removal of hedgerows
  453. 1Removal of hedgerows
  454. 2Removal of important hedgerows
  455. Schedule 12: Arbitration rules
  456. 1Primary objective
  457. 2Time periods
  458. 3Timetable
  459. 4Procedure
  460. 5Arbitrator’s powers
  461. 6Costs
  462. 7Confidentiality
  463. Explanatory note