OpenLegislation

Paragraph 17 Provision of ‘as built’ detailsI1

England, Wales and Scotland

The undertaker must, within 3 months of the completion of the authorised development, provide to the relevant planning authorities details of—

(a)

the location and depth of each part of the Pipeline as it has been constructed;

(b)

any protective measures in place over any part of the Pipeline; and

(c)

the locations of pipeline markers.

Annotations

Commencement

I1

Sch. 2 para. 17 in force at 11.4.2024, see art. 1(2)