Work No. 1 – OCGT power station, being an open cycle gas turbine generating station with a gross capacity of up to 299 megawatts, comprising—

(a)

gas turbine and turbine hall buildings;

(b)

electrical generator;

(c)

stack;

(d)

auxiliary cooling equipment or system;

(e)

gas turbine air intake filters;

(f)

banks of finfan coolers;

(g)

nitrogen oxide emissions control equipment;

(h)

transformers;

(i)

a switchyard, associated switch gear and ancillary equipment;

(j)

a gas receiving area, gas control facilities and gas reception building;

(k)

lubricating oil, hydraulic oil and chemical storage tanks and equipment;

(l)

continuous emissions monitoring system;

(m)

raw water and fire water storage tanks;

(n)

water treatment facilities, demineralised water treatment works, including storage tanks;

(o)

oily water and waste water treatment plant building and basin;

(p)

fire fighting equipment, buildings and distribution pipework;

(q)

permanent plant laydown area;

(r)

auxiliary plant, buildings, enclosures and structures;

(s)

mechanical, electrical, gas, telecommunications and water networks, pipework, cables, racks, infrastructure, instrumentation and utilities, including connections between parts of this Work No. 1 and Work Nos 4, 5 and 6;

(t)

workshop buildings and stores;

(u)

electrical, control, administration and welfare buildings; F1...

(v)

storm water attenuation system; F2and

(w)

synchronous condenser.

Annotations

Textual amendments

F1

Word in Sch. 1 omitted (1.2.2023) by The Immingham Open Cycle Gas Turbine (Amendment) Order 2023 (S.I. 2023/119), arts. 1, 4(a)

F2

Words in Sch. 1 inserted (1.2.2023) by The Immingham Open Cycle Gas Turbine (Amendment) Order 2023 (S.I. 2023/119), arts. 1, 4(b)

Commencement

I1

Sch. 1 in force at 1.9.2020, see art. 1