Paragraph 5 Detailed designI1
England and Wales
In relation to any part of the authorised development comprised in Work No. 1 no development of that part may commence, save for the permitted preliminary works, until details of the following for that part have been submitted to and, in respect of sub-paragraph (d) after consultation with the highway authority, approved by the relevant planning authority—
the siting, layout, scale and external appearance, including the colour, materials and surface finishes of all new permanent buildings and structures;
finished floor levels;
hard standings;
the internal vehicular access and circulation roads, loading and unloading, vehicle parking and turning facilities, cycle parking and routes, and pedestrian facilities and routes; and
landscaping
The details submitted pursuant to sub-paragraph (1) must be in accordance with the parameters set out in F1Schedule 12 (design parameters) .
No part of the authorised development comprised in Work No. 2 may commence, save for the permitted preliminary works, until details of the following for that part have been submitted to and, after consultation with the highway authority, approved by the relevant planning authority—
construction access;
operational access;
vehicle parking; and
haul routes.
No part of the authorised development comprised in Work No. 3 may commence, save for the permitted preliminary works, until details of the following for that part have been submitted to and, in respect of sub-paragraphs (a), (d) and (e) after consultation with the highway authority, approved by the relevant planning authority—
hard standings, laydown and open storage areas;
contractor compounds and construction staff welfare facilities;
gatehouse;
vehicle parking and cycle storage facilities; and
the internal vehicular access and circulation roads, loading and unloading, vehicle parking and turning facilities, cycle parking and routes, and pedestrian facilities and routes.
No part of the authorised development comprised in Work Nos. 4 and 5, save for the permitted preliminary works, may commence until details of the following for that part have been submitted to and, after consultation with National Grid, approved by the relevant planning authority—
the route and method of installation of the gas pipeline; and
the route and method of electrical connection works comprising overground electrical cables, and control systems and cables.
No part of the authorised development comprised in Work No. 6 may commence, save for the permitted preliminary works, until details of the following for that part have been submitted to and, after consultation with the Environment Agency and Anglian Water, approved by the relevant planning authority—
the route and method of construction of any utilities and services connections including water pipes, connections, pumps, tanks, structures and ancillary equipment; telecommunications cables and equipment; electrical cables, connections and ancillary equipment; and control systems and cables; and
water connection works, comprising underground and overground pipes, plant apparatus, enclosures and structures, and supply cables, transformers and control system cables.
Work Nos. 1, 2, 3, 4, 5 and 6 must be carried out in accordance with the approved details unless otherwise agreed with the relevant planning authority.
Annotations
Textual amendments
- F1
Words in Sch. 2 para. 5(2) substituted (17.5.2021) by The Immingham Open Cycle Gas Turbine (Correction) Order 2021 (S.I. 2021/581), art. 1, Sch.
Commencement
- I1
Sch. 2 para. 5 in force at 1.9.2020, see art. 1