Paragraph 137 I1
England and Wales
Before commencing any part of the authorised development which would have an effect on the operation or maintenance of the pipelines and access to them, the undertaker must submit to TLOR plans and sections of the proposed works and such further particulars as TLOR may, within 28 days from the day on which plans and sections are submitted under this paragraph, reasonably require.
Annotations
Commencement
- I1
Sch. 9 para. 137 in force at 1.9.2020, see art. 1