Paragraph 79 Carbon dioxide export connections worksI1

England, Wales and Scotland

(1)

Before beginning to construct any carbon dioxide export connection work, or any part of it, the undertaker must submit to NGC plans of the relevant carbon dioxide export connection work (or part of it) and such further particulars available to it as NGC may request within 28 days of receipt of the plans reasonably requested.

(2)

Any carbon dioxide export connection work must not be constructed except in accordance with such plans as may be approved in writing by NGC.

Annotations

Commencement

I1

Sch. 10 para. 79 in force at 29.12.2022, see art. 1