The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022

S.I. 2022/1396 · Made 7 December 2022 · Extends to England, Wales and Scotland

Up to date with all changes known to legislation.gov.uk, revised to 20 April 2023.

Infrastructure Planning

Made 7th December 2022

Coming into force 29th December 2022

An application has been made to the Secretary of State under section 37 of the Planning Act 2008f1 (“the 2008 Act”) in accordance with the Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009f2 for an order granting development consent.

The application has been examined by the Examining Authority appointed by the Secretary of State pursuant to Chapter 3 of Part 6 of the 2008 Act. The examination was carried out in accordance with Chapter 4 of Part 6 of the 2008 Act and the Infrastructure Planning (Examination Procedure) Rules 2010f3. The Examining Authority has submitted a report and recommendation to the Secretary of State under section 83 of the 2008 Act.

The Secretary of State has considered the report and recommendations of the Examining Authority, has considered the environmental information in accordance with regulation 4 of the Infrastructure Planning (Environmental Impact Assessment) Regulations 2017f4 and has had regard to the documents and matters referred to in section 104(2)f5 of the 2008 Act.

The Secretary of State, having decided the application, has determined to make an order giving effect to the proposals comprised in the application on terms that in the opinion of the Secretary of State are not materially different from those proposed in the application.

Accordingly, the Secretary of State, in exercise of the powers conferred by sections 114, 115, 120 and 149A of the 2008 Act, makes the following Order—

Annotations to the whole text

Footnotes

f1

2008 c. 29. Parts 1 to 7 were amended by Chapter 6 of Part 6 of the Localism Act 2011 (c. 20). Part 7 was amended by S.I. 2017/16.

f2

S.I. 2009/2264, as amended by S.I. 2012/635 and S.I. 2013/522. There are other amendments to the Regulations which are not relevant to this Order.

f3

S.I. 2010/103 amended by S.I. 2012/635.

f4

S.I. 2017/572 amended by S.I. 2018/695, S.I. 2018/942.

f5

Section 104 was amended by section 58(5) of the Marine and Coastal Access Act 2009 (c. 23) and by section 128(2) and Schedule 13, paragraphs 1 and 49(1) to (6) of the Localism Act 2011 (c. 20).

Contents

  1. Part 1: PRELIMINARY
  2. 1Citation and commencement
  3. 2Interpretation
  4. Part 2: PRINCIPAL POWERS
  5. 3Development consent etc. granted by the Order
  6. 4Maintenance of authorised development
  7. 5Operation of authorised development
  8. 6Benefit of the Order
  9. 7Consent to transfer benefit of the Order
  10. 8Application and modification of statutory provisions
  11. Part 3: STREETS
  12. 9Street works
  13. 10Power to alter layout, etc., of streets
  14. 11Construction and maintenance of new or altered means of access
  15. 12Access to works
  16. 13Agreements with street authorities
  17. Part 4: SUPPLEMENTAL POWERS
  18. 14Discharge of water
  19. 15Authority to survey and investigate the land
  20. 16Temporary interference with canal and public rights of navigation
  21. 17Use of private roads for construction
  22. Part 5: POWERS OF ACQUISITION
  23. 18Compulsory acquisition of land
  24. 19Statutory authority to override easements and other rights
  25. 20Time limit for exercise of authority to acquire land compulsorily
  26. 21Compulsory acquisition of rights etc.
  27. 22Private rights
  28. 23Application of the 1981 Act and Part 1 of the 1961 Act
  29. 24Acquisition of subsoil or airspace only
  30. 25Modification of Part 1 of the 1965 Act
  31. 26Rights under or over streets
  32. 27Temporary use of land for carrying out the authorised development
  33. 28Temporary use of land for maintaining the authorised development
  34. 29Statutory undertakers
  35. 30Apparatus and rights of statutory undertakers in streets
  36. 31Recovery of costs of new connections
  37. Part 6: OPERATIONS
  38. 32Crown Rights
  39. 33Felling or lopping of trees and removal of hedgerows
  40. 34Protective works to buildings
  41. Part 7: MISCELLANEOUS AND GENERAL
  42. 35Protective provision
  43. 36Restoration works
  44. 37Application of landlord and tenant law
  45. 38Operational land for purposes of the 1990 Act
  46. 39Deemed marine licence under the Marine and Coast Access Act 2009
  47. 40Defence to proceedings in respect of statutory nuisance
  48. 41Certification of plans etc.
  49. 42Service of notices
  50. 43Procedure in relation to certain approvals etc.
  51. 44Arbitration
  52. 45Guarantees in respect of payment of compensation
  53. Signature
  54. Schedule 1AUTHORISED DEVELOPMENT
  55. Schedule 2: REQUIREMENTS
  56. 1Interpretation
  57. 2Commencement of the authorised development
  58. 3Notice of commencement and completion of commissioning
  59. 4Notice of commencement of commercial use
  60. 5Detailed design
  61. 6Landscaping and biodiversity protection management and enhancement
  62. 7External lighting
  63. 8Highway accesses
  64. 9Means of enclosure
  65. 10Site security
  66. 11Fire prevention
  67. 12Surface water drainage
  68. 13Foul water drainage
  69. 14Flood risk mitigation
  70. 15Contaminated land and groundwater
  71. 16Archaeology
  72. 17Construction environmental management plan
  73. 18Protection of highway surfaces
  74. 19Temporary haul road (traffic management and protection)
  75. 20Temporary haul road (biodiversity protection)
  76. 21Temporary haul road (removal and restoration)
  77. 22Temporary haul road (prior approval of restoration scheme)
  78. 23Pilfrey laydown (design)
  79. 24Pilfrey laydown (removal and restoration)
  80. 25Construction traffic management plan
  81. 26Construction worker travel plan
  82. 27Construction hours
  83. 28Control of noise and vibration - construction
  84. 29Control of noise - operation
  85. 30Piling and penetrative foundation design
  86. 31Restoration of land used temporarily for construction
  87. 32Combined heat and power
  88. 33Carbon capture and compression plant
  89. 34Aviation warning lighting
  90. 35Air safety
  91. 36Local liaison committee
  92. 37Employment, skills and training plan
  93. 38Decommissioning
  94. 39Requirement for written approval
  95. 40Approved details and amendments to them
  96. 41Amendments agreed by the relevant planning authority
  97. Schedule 3STREETS SUBJECT TO STREET WORKS
  98. Schedule 4STREETS SUBJECT TO PERMANENT ALTERATIONS OF LAYOUT
  99. Schedule 5ACCESS - THOSE PARTS OF THE ACCESS TO BE MAINTAINED AT THE PUBLIC EXPENSE
  100. Schedule 6: NEW RIGHTS
  101. 1Interpretation
  102. Schedule 7: MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS
  103. 1Compensation enactments
  104. 2Compensation enactments
  105. 3Compensation enactments
  106. 4Application of Part 1 of the 1965 Act
  107. 5Application of Part 1 of the 1965 Act
  108. Schedule 8LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
  109. Schedule 9: PROCEDURE FOR DISCHARGE OF REQUIREMENTS
  110. 1Paragraph 1
  111. 2Applications made under Requirements
  112. 3Further information and consultation
  113. 4Fees
  114. 5Appeals
  115. Schedule 10: PROTECTIVE PROVISIONS
  116. Part 1: FOR THE PROTECTION OF NATIONAL GRID AS ELECTRICITY AND GAS UNDERTAKER
  117. 1Application
  118. 2Interpretation
  119. 3On Street Apparatus
  120. 4Apparatus of National Grid in stopped up streets
  121. 5Protective works to buildings
  122. 6Acquisition of land
  123. 7Removal of apparatus
  124. 8Facilities and rights for alternative apparatus
  125. 9Retained apparatus: protection of electricity undertaker
  126. 10Retained apparatus: protection of gas undertaker
  127. 11Expenses
  128. 12Indemnity
  129. 13Enactments and agreements
  130. 14Co-operation
  131. 15Access
  132. 16Arbitration
  133. 17Notices
  134. Part 2: FOR THE PROTECTION OF CANAL AND RIVER TRUST
  135. 18Interpretation
  136. 19Powers requiring the Canal and River Trust’s consent
  137. 20Fencing
  138. 21Survey of waterway
  139. 22Approval of plans, protective works etc.
  140. 23Design of works
  141. 24Notice of works
  142. 25Lighting
  143. 26Construction of specified works
  144. 27Prevention of pollution
  145. 28Access to work – provision of information
  146. 29Alterations to the waterway
  147. 30Maintenance of works
  148. 31Repayment of the Canal and River Trust’s fees, etc.
  149. 32Making good of detriment; compensation and indemnity, etc.
  150. 33Arbitration
  151. 34Capitalised sums
  152. Part 3: FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS
  153. 35Paragraph 35
  154. 36Paragraph 36
  155. 37Paragraph 37
  156. 38Paragraph 38
  157. 39Paragraph 39
  158. 40Paragraph 40
  159. 41Paragraph 41
  160. 42Paragraph 42
  161. 43Paragraph 43
  162. 44Paragraph 44
  163. Part 4: FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
  164. 45Paragraph 45
  165. 46Paragraph 46
  166. 47Paragraph 47
  167. 48Paragraph 48
  168. 49Paragraph 49
  169. Part 5: FOR THE PROTECTION OF RAILWAY INTERESTS
  170. 50Paragraph 50
  171. 51Paragraph 51
  172. 52Paragraph 52
  173. 53Paragraph 53
  174. 54Paragraph 54
  175. 55Paragraph 55
  176. 56Paragraph 56
  177. 57Paragraph 57
  178. 58Paragraph 58
  179. 59Paragraph 59
  180. 60Paragraph 60
  181. 61Paragraph 61
  182. 62Paragraph 62
  183. 63Paragraph 63
  184. 64Paragraph 64
  185. 65Paragraph 65
  186. 66Paragraph 66
  187. 67Paragraph 67
  188. 68Paragraph 68
  189. 69Paragraph 69
  190. 70Paragraph 70
  191. 71Paragraph 71
  192. Part 6: FOR THE PROTECTION OF NATIONAL GRID CARBON LIMITED
  193. 72Application
  194. 73Application
  195. 74Application
  196. 75Interpretation
  197. 76Interaction with the NGC Pipeline Network
  198. 77Carbon dioxide export connections works
  199. 78Carbon dioxide export connections works
  200. 79Carbon dioxide export connections works
  201. 80Carbon dioxide export connections works
  202. 81Carbon dioxide export connections works
  203. 82On street apparatus
  204. 83Acquisition of land
  205. 84Protective works to buildings
  206. 85Removal of NGC apparatus
  207. 86Facilities and rights for alternative apparatus
  208. 87Specified works plan approval
  209. 88Specified works plan approval
  210. 89Expenses and costs
  211. 90Indemnity
  212. 91Co-operation
  213. 92Disputes
  214. Part 7: FOR THE PROTECTION OF NORTHERN POWERGRID
  215. 93Paragraph 93
  216. 94Paragraph 94
  217. 95Paragraph 95
  218. 96Paragraph 96
  219. 97Paragraph 97
  220. 98Paragraph 98
  221. 99Paragraph 99
  222. 100Paragraph 100
  223. 101Paragraph 101
  224. 102Paragraph 102
  225. 103Paragraph 103
  226. 104Paragraph 104
  227. 105Paragraph 105
  228. Schedule 11: DESIGN PARAMETERS
  229. 1Paragraph 1
  230. 2Paragraph 2
  231. 3Paragraph 3
  232. 4Paragraph 4
  233. Schedule 12DOCUMENTS AND PLANS TO BE CERTIFIED
  234. Schedule 13: DEEMED MARINE LICENCE UNDER PART 4 (MARINE LICENSING) OF THE MARINE AND COASTAL ACCESS ACT 2009 / DEEMED MMO LICENCE PROVISIONS
  235. Part 1: INTRODUCTION
  236. 1Paragraph 1
  237. Part 2: DETAILS OF LICENSED MARINE ACTIVITIES
  238. 2Paragraph 2
  239. 3Paragraph 3
  240. 4Paragraph 4
  241. 5Paragraph 5
  242. 6Paragraph 6
  243. Part 3: CONDITIONS
  244. 7General
  245. 8Notifications and Inspections
  246. 9Pre-construction
  247. 10Pre-construction
  248. 11Pre-construction
  249. 12Pre-construction
  250. 13Pre-construction
  251. 14During Construction, Operation and Maintenance
  252. 15During Construction, Operation and Maintenance
  253. 16During Construction, Operation and Maintenance
  254. 17During Construction, Operation and Maintenance
  255. 18During Construction, Operation and Maintenance
  256. 19During Construction, Operation and Maintenance
  257. 20During Construction, Operation and Maintenance
  258. 21During Construction, Operation and Maintenance
  259. 22During Construction, Operation and Maintenance
  260. 23During Construction, Operation and Maintenance
  261. 24Post Construction
  262. 25Post Construction
  263. 26Post Construction
  264. 27Conditions Discharge
  265. Explanatory note