Paragraph 24 Pilfrey laydown (removal and restoration)I1

England, Wales and Scotland

(1)

The authorised development comprised in Work No. 9A and located within the area described in the Pilfrey laydown plans shall be removed and the land restored to its former condition no later than 3 months following the completion of commissioning in accordance with a scheme of work submitted to and approved by the relevant planning authority.

(2)

The scheme authorised under (1) must be implemented in full unless otherwise agreed with the relevant planning authority.