Schedule 2 REQUIREMENTS
England, Wales and Scotland
- 1Interpretation
- 2Commencement of the authorised development
- 3Notice of commencement and completion of commissioning
- 4Notice of commencement of commercial use
- 5Detailed design
- 6Landscaping and biodiversity protection management and enhancement
- 7External lighting
- 8Highway accesses
- 9Means of enclosure
- 10Site security
- 11Fire prevention
- 12Surface water drainage
- 13Foul water drainage
- 14Flood risk mitigation
- 15Contaminated land and groundwater
- 16Archaeology
- 17Construction environmental management plan
- 18Protection of highway surfaces
- 19Temporary haul road (traffic management and protection)
- 20Temporary haul road (biodiversity protection)
- 21Temporary haul road (removal and restoration)
- 22Temporary haul road (prior approval of restoration scheme)
- 23Pilfrey laydown (design)
- 24Pilfrey laydown (removal and restoration)
- 25Construction traffic management plan
- 26Construction worker travel plan
- 27Construction hours
- 28Control of noise and vibration - construction
- 29Control of noise - operation
- 30Piling and penetrative foundation design
- 31Restoration of land used temporarily for construction
- 32Combined heat and power
- 33Carbon capture and compression plant
- 34Aviation warning lighting
- 35Air safety
- 36Local liaison committee
- 37Employment, skills and training plan
- 38Decommissioning
- 39Requirement for written approval
- 40Approved details and amendments to them
- 41Amendments agreed by the relevant planning authority