Paragraph 22 Temporary haul road (prior approval of restoration scheme)I1
England, Wales and Scotland
(1)
No later than 36 months following commencement of the construction of Work No. 1, a scheme for the removal of the temporary haul road, road bridges and associated infrastructure and restoration of Work No. 10A including the incorporation of biodiversity enhancements and a timetable for implementation, shall be submitted to and approved in writing by the relevant planning authority.
(2)
The scheme authorised under (1) must be implemented in full unless otherwise agreed with the relevant planning authority.