Paragraph 26 Construction worker travel planI1
England, Wales and Scotland
No part of the authorised development may commence, save for the permitted preliminary works, until a construction workers travel plan has been submitted to and, after consultation with the highway authority, approved by the relevant planning authority.
The plan submitted and approved must be in accordance with the framework construction workers travel plan.
The plan submitted and approved must include—
measures to promote the use of sustainable transport modes to and from the authorised development by construction staff;
provision as to the responsibility for, and timescales of, the implementation of those measures;
details of parking for construction personnel within the construction sites; and
a monitoring and review regime.
The approved plan must be implemented within three months of commencement of the authorised development and must be maintained throughout the construction of the authorised development unless otherwise agreed with the relevant planning authority.
Annotations
Commencement
- I1
Sch. 2 para. 26 in force at 29.12.2022, see art. 1