Paragraph 33 Carbon capture and compression plantI1

England, Wales and Scotland

(1)

No part of the authorised development may commence, save for the permitted preliminary works and Work No.9B and Work No.9C, until details of the following have been submitted to and approved by the relevant planning authority—

(a)

evidence that Development Consent is in place for the construction of the National Grid Carbon Gathering Network;

(b)

evidence that a Carbon Dioxide Storage Licence for the intended storage site for the National Grid Carbon Gathering Network is in place;

(c)

evidence that an Environmental Permit is in place for Work No. 1; and

(d)

evidence of any pipeline works authorisation required by section 14 of the Petroleum Act 1998 for offshore pipeline works.

(2)

Prior to the start of commissioning of the authorised development, the undertaker must not without the consent of the Secretary of State—

(a)

dispose of any interest in the land required for Work No. 1C or Work No. 7; or

(b)

do anything, or allow anything to be done or to occur, which may reasonably be expected to diminish the undertaker’s ability, within two years of such action or occurrence, to prepare Work No. 1C and Work No. 7 for construction.

(3)

Work No. 1A may not be brought into commercial use without Work No. 1C and Work No. 7A also being brought into commercial use.