Schedule 8 LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKENI1
England, Wales and Scotland
Table 5
| (1) Number of plots shown on the land plans | (2) Purpose for which temporary possession may be take | (3) Relevant part of the authorised development |
|---|---|---|
| 47 | Access and construction worksite | Work No. 2A |
| 40b, 43, 56, 58, 59 | Access and construction worksite. | Work No. 3B |
| 32a | Access and construction worksite | Work No. 6 |
| 1, 2, 4, 5, 6, 7, 8, 9, 10, 26 | Access and construction worksite. | Work No. 8A |
| 40b, 55, 56, 58, 59, 67 | Access and construction worksite. | Work No. 8C |
| 1, 2, 3, 4, 10, 11, 12, 16a, 17, 17a, 18, 19, 20, 21, 22, 23, 25, 26, 27, 28, 29, 30, 32, 32a, 33, 34, 37, 38, 39, 49, 50a, 50, 51, 61, 62, 63, 72a | Access and construction worksite, use of the land for temporary laydown areas including any ancillary works necessary to facilitate the use of that land, storage, placing of temporary cranes and works associated with the re-instatement of the land. Works compound and welfare facilities, storage, laydown areas, and re-instatement of laydown areas. | Work Nos. 9A, 9B and 9C |
| 13, 14, 16, 16a, 17a, 17b, 31, 32a, 46, 47, 48, 49a, 50, 50a, 51, 53, 54, 62, 63, 72, 72a, 73, 74, 78, 79, 93, 95, 101, 119, 131, 135, 136, 144, 145, 165, 165a 170 | Access and construction worksite, including temporary haul road and any ancillary works necessary to facilitate the use of that land as a temporary haul road and re-instatement of the land. | Work No. 10A |
| 136, 146, 149, 155 | Access, inspection and repair, construction worksite and placing of temporary cranes. | Work No. 10B |
| 68 | Access and construction worksite. | Work No. 11A |
Annotations
Commencement
- I1
Sch. 8 in force at 29.12.2022, see art. 1