OpenLegislation

Paragraph 8 Safety managementI1

England, Wales and Scotland

(1)

No authorised development shall commence until the Secretary of State, in consultation with the MCA, has given written approval of a plan for an active safety management system in accordance with the MCA recommendations in Annex 4 of the document MGN 371 Offshore Renewable Energy Installations (OREIs) – Guidance on UK Navigational Practice, Safety and Emergency Response Issues.

(2)

No authorised development shall commence until the Secretary of State, in consultation with the MCA, has given written approval of a plan providing full details of the emergency co-operation plans for the construction, operation and decommissioning phases of the authorised development which satisfies the MCA recommendations in Annex 5 of the document MGN 371 Offshore Renewable Energy Installations (OREIs) – Guidance on UK Navigational Practice, Safety and Emergency Response Issues.

(3)

The active safety management system and emergency response and co-operation plans must be implemented as approved unless otherwise agreed in writing by the Secretary of State.

Annotations

Commencement

I1

Sch. 1 para. 8 in force at 20.2.2013, see art. 1