Paragraph 13 Contaminated land and groundwater – generalI1
England and Wales
No part of the authorised development may commence until, for that part, a written scheme produced in line with CLR11 Model Procedures (which may be included in the CEMP) to deal with the contamination of any land, including groundwater, within the Order limits has been submitted to and approved in writing by the relevant planning authority in consultation with the Environment Agency.
The scheme must include an investigation and assessment report, prepared by a specialist consultant and approved in writing by the relevant planning authority, to identify the extent of any contamination and a risk based remedial strategy to be produced and fully implemented, based on the findings of the investigation, to render the land fit for its intended purpose, together with a management plan which sets out long-term monitoring measures with respect to any contaminants remaining on the site.
If during construction of the authorised development contaminated land or groundwater is encountered in excavations of Order land that was not identified in the initial investigation and assessment, then work in the vicinity of that contamination must be suspended, additional investigation and assessment carried out, and the scheme produced under sub-paragraph (1) amended to reflect the results. The amendments and any additional remediation required must be approved by the relevant planning authority in consultation with the Environment Agency prior to any works resuming.
Remediation must be implemented in accordance with the approved scheme.
Prior to commencement of the authorised development (or resumption of works following additional investigation and assessment under sub-paragraph (3)), a verification report demonstrating completion of the remediation works and the effectiveness of the remediation must be submitted to and approved, in writing, by the relevant planning authority in consultation with the Environment Agency. The report must include results of the sampling and monitoring carried out in accordance with the approved remedial strategy to demonstrate that the site remediation criteria have been met.
Annotations
Commencement
- I1
Sch. 1 para. 13 in force at 1.4.2015, see art. 1