Paragraph 14 Contaminated land and groundwater – known contamination on the site of the generating stationI1

England and Wales

The part of the authorised development comprising the generating station must not commence until the remediation permission has been implemented in full and a verification report under Requirement 13(5) has been submitted to and approved in writing by the relevant planning authority.

Annotations

Commencement

I1

Sch. 1 para. 14 in force at 1.4.2015, see art. 1