Paragraph 9 Footpath/Public Rights of Way diversionsI1
England and Wales
No part of the authorised development may commence until a written public rights of way management plan for any sections of public rights of way shown to be extinguished or temporarily closed on the public rights of way temporary closures and permanent stopping up plan for that part has been approved in writing by the relevant planning authority in consultation with the relevant highway authority.
The public rights of way management plan for the relevant part must include details of and a specification for the provisions of the temporary bridleway to be provided as part of Work No. 9.
The public rights of way management plan and the provision of the temporary bridleway must thereafter be implemented as approved.