Paragraph 19 Capitalised sumsI1

England and Wales

Any capitalised sum which is required to be paid under this Schedule shall be calculated by multiplying the cost of the maintenance or renewal works to the waterway necessitated as a result of the operation of the authorised development by the number of times that the maintenance or renewal works will be required during the operation of the authorised development.

Annotations

Commencement

I1

Sch. 8 para. 19 in force at 1.4.2015, see art. 1

Notes on For the protection of Canal & River Trust

Textual amendments

F1

Words in Sch. 8 sub-heading substituted (23.7.2016) by The Knottingley Power Plant (Correction) Order 2016 (S.I. 2016/797), art. 1, Sch.